
2021 Easily pass C_TS422_2020 Exam with our Dumps & PDF Test Engine
C_TS422_2020 PDF Pass Leader, C_TS422_2020 Latest Real Test
SAP S/4HANA Production Planning and Manufacturing Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books | Weighting |
|---|---|---|
| Introduction to SAP S/4HANA Supply Chain Planning | Outline both motivation and background of SAP S/4HANA, describe its main components, the lines of business, and the SAP User Experience strategy. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Advanced Planning in SAP S/4HANA | Outline the basics and master data of advanced planning, explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Lean Manufacturing in SAP S/4HANA | Identify repetitive manufacturing specific master data, explain line load planning and confirmation, outline Kanban master data and Kanban processes. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Master Data in SAP S/4HANA | Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version. TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Demand Management in SAP S/4HANA | Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Capacity Planning in SAP S/4HANA | Outline best practices for using SAP S/4HANA, describe the SAP HANA database concept and new user experience with SAP Fiori, outline the capabilities of embedded analytics. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Process Orders in SAP S/4HANA | Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP). TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Material Requirements Planning in SAP S/4HANA | Select and apply planning strategies, use the planning table, characterize long-term planning and master production scheduling, outline MRP basics and steps of MRP, and describe lot size procedures. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Production Orders in SAP S/4HANA | Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation. TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Introduction to SAP S/4HANA Production Planning | Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
SAP S/4HANA Production Planning and Manufacturing Certification Exam Details:
| Number of Questions | 80 |
| Reference Books | TS421, TS422 (SAP S/4HANA 2020) TS421 (SAP S/4HANA 1909), TS422 (SAP S/4HANA 1909) |
| Exam Name | SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing |
| Passing Score | C_TS422_2020 - 56% C_TS422_1909 - 55% |
| Level | Associate |
| Exam Price | $550 (USD) |
| Exam Code | C_TS422_2020 |
| Sample Questions | SAP S/4HANA Production Planning and Manufacturing Certification Sample Questions |
| Schedule Exam | SAP Training |
| Duration | 180 mins |
NEW QUESTION 15
When can the material availability check occur automatically in a production order? Note: There are 2 correct answers to this question.
- A. At order release
- B. At order settlement
- C. At order confirmation
- D. At order creation
Answer: A,D
NEW QUESTION 16
What are some uses for the low-level code assigned to each material? Note: There are 2correct answers to this question.
- A. It is used by ATP to determine the priority of alternative components.
- B. It is used in MRP to determine the sequence in which materials are planned.
- C. It is used by engineering to identify sub items in an engineering bill of material(BOM).
- D. It is used by product costing to determine how costs are rolled up.
Answer: B,D
NEW QUESTION 17
You want to insert an operation at a certain time on a work center. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?
- A. The previously dispatched operation stays as is the new operation is insertedafter the dispatched operation.
- B. The previously dispatched operation stays assist the new operation is inserted before the dispatched operation.
- C. The new operation is inserted at the desired time; the previously dispatched operation is moved forward.
- D. The new operation is inserted at the desired time the previously dispatched operation is moved backward.
Answer: D
NEW QUESTION 18
Which time elements are relevant for lead t me scheduling of a product on order? Note: There are 2 correct answers to this question.
- A. Planned delivery time
- B. Setup time
- C. Total replenishment lead time
- D. Float after production
Answer: A,D
NEW QUESTION 19
What data can you maintain in the sub items of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. Installation point
- B. Scrap percentage
- C. Quantity
- D. Item type
Answer: A,C
NEW QUESTION 20
For what production type are production orders used?
- A. Discrete manufacturing processes
- B. Replenishment controlled by control cycles
- C. Process manufacturing processes
- D. Period and quantity-oriented production
Answer: A
NEW QUESTION 21
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
- A. Select an alternative mode on a resource.
- B. Reduce the planning window.
- C. Execute a new production planning run.
- D. Adjust the available capacity.
- E. Form optimum sequences to reduce setup times.
Answer: A,D,E
NEW QUESTION 22
Which actions does the system perform by default when you save aconfirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
- A. Posting of production costs to the production cost collector
- B. Archiving of documents for assembly scrap
- C. Posting of goods receipt for the product
- D. Reduction of associated capacity requirements
- E. Material staging for next order in sequence
Answer: A,C,D
NEW QUESTION 23
What is the purpose of collective orders?
- A. To combine order management of co-products and by-products with the main product
- B. To manage production orders for an entirefinished product on multiple levels
- C. To post any component withdrawals single back flush with order confirmation
- D. To post production costs ona cost collector instead of the production order
Answer: B
NEW QUESTION 24
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Functional Location BOM
- B. Class BOM
- C. Work Center BOM
- D. Sales Order BOM
Answer: A,D
NEW QUESTION 25
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stockis zero and the discontinuation date is in the past?
- A. Kanban
- B. Material requirements planning
- C. Production order release
- D. Back flushing
Answer: B
NEW QUESTION 26
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.
- A. Change of the storage bin
- B. Creation of a purchasing contract
- C. Change of the material'sprocurement type
- D. Creation of a sales order
- E. Creation of dependent requirements
Answer: C,D,E
NEW QUESTION 27
Which time elements can be reduced by a reductionstrategy? Note: There are 3 correct answers to this question.
- A. Wait time
- B. Goods receipt processing time
- C. Queue time
- D. Float after production
- E. Move time
Answer: C,D,E
NEW QUESTION 28
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. By industry
- B. By period
- C. By material type
- D. By plant
Answer: B,D
NEW QUESTION 29
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.
- A. To determine the work in progress along the production line
- B. To stage different components for a production line simultaneously
- C. To provide timely updates of inventory management for the staged components
- D. To reduce the totalproduction lead time for along production line
Answer: A,C
NEW QUESTION 30
The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?
- A. Use the reorder point.
- B. Use the minimum order quantity.
- C. Use the MRP type for vendor managed inventory.
- D. Use the fixed lot size procedure.
Answer: D
NEW QUESTION 31
If you use floats to limit dispatching in capacity planning, what type of time element can be reduced by strategy settings while dispatching?
- A. Minimum wait time
- B. Production time
- C. Goods receipt processing time
- D. Queue time
Answer: D
NEW QUESTION 32
When working with both cross-plant and plant-specific material statuses in the mater al master, which status has the highest priority?
- A. The cross-plant status
- B. The most restrictive status
- C. The plant-specific status
- D. The least restrictive status
Answer: B
NEW QUESTION 33
You are working with planning strategy 40 (Planning-with-final assembly). When does consumption of planned independent requirements take place?
- A. When you create a sales order
- B. When the MRP results are saved
- C. When you deliver a sales order
- D. When you create a planned order
Answer: A
NEW QUESTION 34
You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.
- A. Individualconversion
- B. Full conversion
- C. Partial conversion
- D. Order release
Answer: B,C
NEW QUESTION 35
......
C_TS422_2020 Dumps Ensure Your Passing: https://dumpsvce.exam4free.com/C_TS422_2020-valid-dumps.html
